📍 Martin's Pharmacy 6282 — 409 South Street, Front Royal VA, 22630
Dec 30, 2024 → Oct 16, 2025
✅ Completed
PSM
SLA Clock
Last business day of December 2024 · Target: Dec 31, 2024
✗ SLA Missed (78 biz days late)
Active: 80 biz days
Paused: 120 biz days
🕐 Clock stopped: Completed (Oct 16, 2025)
63d
▶ Clock Running
Status: Created
Dec 30 → Apr 1, 2025
63 business days (counted)
Running total: 63 of ? biz days used
⏸114d
⏸ Clock Paused
Status: Ready for Release
Apr 1 → Sep 12, 2025
114 business days (not counted)
▶ Clock Running
Status: Assigned
Sep 12 → Sep 12, 2025
0 business days (counted)
Running total: 63 of ? biz days used
▶ Clock Running
Status: Scheduled
Sep 12 → Sep 15, 2025
1 business day (counted)
Running total: 64 of ? biz days used
▶ Clock Running
Status: Reschedule
Sep 15 → Sep 17, 2025
2 business days (counted)
Running total: 66 of ? biz days used
⏸ Clock Paused
Status: Ready for Release
Sep 17 → Sep 25, 2025
6 business days (not counted)
▶ Clock Running
Status: Assigned
Sep 25 → Oct 1, 2025
4 business days (counted)
Running total: 70 of ? biz days used
▶ Clock Running
Status: Scheduled
Oct 1 → Oct 16, 2025
10 business days (counted)
Running total: 80 of ? biz days used
▶ Clock Running
Status: Tech On Site
Oct 16 → Oct 16, 2025
0 business days (counted)
Running total: 80 of ? biz days used
Created: Dec 30, 2024Completed: Oct 16, 2025
Show SLA Clock Detail (9 periods)
Period
Status
Clock
Biz Days
Running Total
Dec 30 → Apr 1
Created
▶ Running
63
63
Apr 1 → Sep 12
Ready for Release
⏸ Paused
114
—
Sep 12 → Sep 12
Assigned
▶ Running
0
63
Sep 12 → Sep 15
Scheduled
▶ Running
1
64
Sep 15 → Sep 17
Reschedule
▶ Running
2
66
Sep 17 → Sep 25
Ready for Release
⏸ Paused
6
—
Sep 25 → Oct 1
Assigned
▶ Running
4
70
Oct 1 → Oct 16
Scheduled
▶ Running
10
80
Oct 16 → Oct 16
Tech On Site
▶ Running
0
80
Holding184.6d (excluded)
Coordinators19.4d
Field Work0.5d
Billing0.3d
✗ SLA Missed
Holding(excluded from total)
184.6 days
Coordinators
19.4 days
Over SLA
Field Work
0.5 days
Billing
0.3 days
Created: Dec 30, 2024
Due: Dec 31, 2025
Completed: Oct 16, 2025 (76 days early)
📅
200.3 daysTotal Age
⏱️
115.0d in Ready for ReleaseLongest Stage
🔄
12 transitionsStatus Changes
⚠️
13.3d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
3 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 429 days old
🚨
Primary Delay115.0 days stuck in "Ready for Release"
⏱️
Total Delay13.3 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
63.3d
Ready for Release
121.3d
Assigned
4.8d / 0.5d SLA
Scheduled
12.0d / 2.0d SLA
Reschedule
2.6d / 2.0d SLA
Tech On Site
0.1d / 1.0d SLA
Completed
0.4d / 1.0d SLA
Closed
1.1d / 1.0d SLA
Ready to Bill
0.3d / 1.0d SLA
💬 Activities, Notes & Communications
🔧Work Performed
10/16/25 PC- PM
Technician Findings upon arrival: Found unit fully functional.
Actions Taken/Work Performed: Complete Higi PM.
Final Resolution: Unit passed all function test.
🔍Technician Findings
10/16/25 PC- PM
Technician Findings upon arrival: Found unit fully functional.
Actions Taken/Work Performed: Complete Higi PM.
Final Resolution: Unit passed all function test.
⚠️Problem Description
Please Perform a PM on this Kiosk and attach all required photos from Checklist Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance%20009%20DCR652.pdf
📄Description
Merge KMY Kiosk
📅
WO-01226922 - Preventive Maintenance - KMY8202F - Front Royal - Martin's Pharmacy 6282
Oct 16, 2025 3:30pm – 4:30pm
Work Order: WO-01226922
Account: HIGI LLC
Customer Case Number:
Location: Martin's Pharmacy 6282
Address: 409 South Street, Front Royal, VA 22630
Manufacturer: Merge SH Holdings, Inc.
Model #: KMY8202F
Serial #: KMY-120630950-793
Contact Name:
Contact Phone:
Contact Email:
Due Date: 12/31/2025