Work Order 360 View

Detailed work order timeline, KPIs, and analysis

← WO Overview

WO-01229139 ↗ ServiceMax

HIGI LLC • Preventive Maintenance • PSM

📍 Peoria ATC Correctional Center — 607 Main St., Peoria IL, 61602

Dec 30, 2024 → Sep 10, 2025

✅ Completed
PSM
SLA Clock
Last business day of December 2024 · Target: Dec 31, 2024
✗ SLA Missed (81 biz days late)
Active: 83 biz days
Paused: 92 biz days
🕐 Clock stopped: Completed (Sep 10, 2025)
63d
▶ Clock Running
Status: Created
Dec 30 → Apr 1, 2025
63 business days (counted)
Running total: 63 of ? biz days used
⏸62d
⏸ Clock Paused
Status: Ready for Release
Apr 1 → Jun 30, 2025
62 business days (not counted)
▶ Clock Running
Status: Assigned
Jun 30 → Jun 30, 2025
0 business days (counted)
Running total: 63 of ? biz days used
▶ Clock Running
Status: Scheduled
Jun 30 → Jul 9, 2025
6 business days (counted)
Running total: 69 of ? biz days used
▶ Clock Running
Status: Tech On Site
Jul 9 → Jul 9, 2025
0 business days (counted)
Running total: 69 of ? biz days used
▶ Clock Running
Status: Completed
Jul 9 → Jul 9, 2025
0 business days (counted)
Running total: 69 of ? biz days used
▶ Clock Running
Status: Reschedule
Jul 9 → Jul 11, 2025
2 business days (counted)
Running total: 71 of ? biz days used
⏸30d
⏸ Clock Paused
Status: Ready for Release
Jul 11 → Aug 22, 2025
30 business days (not counted)
▶ Clock Running
Status: Assigned
Aug 22 → Aug 22, 2025
0 business days (counted)
Running total: 71 of ? biz days used
▶ Clock Running
Status: Scheduled
Aug 22 → Sep 10, 2025
12 business days (counted)
Running total: 83 of ? biz days used
▶ Clock Running
Status: Tech On Site
Sep 10 → Sep 10, 2025
0 business days (counted)
Running total: 83 of ? biz days used
Created: Dec 30, 2024 Completed: Sep 10, 2025
Show SLA Clock Detail (11 periods)
Period Status Clock Biz Days Running Total
Dec 30 → Apr 1 Created ▶ Running 63 63
Apr 1 → Jun 30 Ready for Release ⏸ Paused 62
Jun 30 → Jun 30 Assigned ▶ Running 0 63
Jun 30 → Jul 9 Scheduled ▶ Running 6 69
Jul 9 → Jul 9 Tech On Site ▶ Running 0 69
Jul 9 → Jul 9 Completed ▶ Running 0 69
Jul 9 → Jul 11 Reschedule ▶ Running 2 71
Jul 11 → Aug 22 Ready for Release ⏸ Paused 30
Aug 22 → Aug 22 Assigned ▶ Running 0 71
Aug 22 → Sep 10 Scheduled ▶ Running 12 83
Sep 10 → Sep 10 Tech On Site ▶ Running 0 83
Holding 157.2d (excluded)
Coordinators 22.5d
Field Work 0.4d
Billing 0.1d
✗ SLA Missed
Holding (excluded from total)
157.2 days
Coordinators
22.5 days
Over SLA
Field Work
0.4 days
Billing
0.1 days
Created: Dec 30, 2024 Due: Dec 31, 2025 Completed: Sep 10, 2025 (112 days early)
📅
175.3 days Total Age
⏱️
63.3d in On Hold Longest Stage
🔄
13 transitions Status Changes
⚠️
16.1d over Total Delay
📦
0 orders, 0 quotes Parts & Quotes
📝
6 lines Work Details
🏠
2 visits On-Site Trips
👤
Self-Scheduled Scheduling
🔄
2 On-Site Visits (1 reschedule)
2 on-site visits — follow-up trip required
👤 Self-scheduled by Mike Huffman — scheduling delays attributed to technician, not coordinators
Visit 1 Jul 9, 2025
Visit 2 Sep 10, 2025

AI Analysis

Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 429 days old
🚨
Primary Delay 63.3 days stuck in "On Hold"
⏱️
Total Delay 16.1 business days over SLA thresholds

SLA vs Actual Time by Status

Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
63.3d
Ready for Release
94.0d
Assigned
0.4d / 0.5d SLA
Scheduled
19.9d / 2.0d SLA
Tech On Site
0.2d / 1.0d SLA
Completed
0.2d / 1.0d SLA
Reschedule
2.2d / 2.0d SLA
Closed
0.0d / 1.0d SLA
Ready to Bill
0.1d / 1.0d SLA

💬 Activities, Notes & Communications

🔒 Internal CSA Notes

ASC CONFIRMED


8/22/25 RCook- Spoke with Melinda Ellis, scheduled for 9/10/25. Arrival time between 9-11AM. Requested that we email a list of equipment/tools that technician will be bringing onsite. This visit will require an escort. Sent email to MHuffman asking him to email Melinda a list of equipment to melinda.ellis@illinois.gov. 


7/9/25 RCook- Technician was denied access to enter due to phone and tools. Placing WO in reschedule status.


7/9/25 RCook- Received message from LYoder the site would not let Alexis in with his keyboard and phone. Asked if paperwork was filled out. Advise LYoder that I asked if a background or anything was needed in order for the technician have access and Justin Ellis stated no.


6/30/25 RCook- Spoke with Justin Ellis, scheduled for 7/9/25. Arrival time between 10AM-12PM. Per Justin background check is not needed.

🔧 Work Performed
9/10/2025 M. Huffman. Completed the PM, field service report and obtained signature from Customer. Was not allowed into facility due to my cell phone and tools that were cleared a week and a half ago warden stated that there’s no exceptions for nobody
🔍 Technician Findings
Kiosk does not show signs of customer damage. Kiosk is fully operational. Yes Was the kiosk unplugged on arrival? No Was not allowed into facility due to my cell phone and tools that were cleared a week and a half ago warden stated that there’s no exceptions for nobody
⚠️ Problem Description
Please Perform a PM on this Kiosk and attach all required photos from the PM Checklist Note this is a Non-retail account and requires a call to schedule. Please navigate to the location page for contact details Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance%20009%20DCR652.pdf
📄 Description
Higi Green Kiosk Hard wired

Timeline

📋
Work Order Created Dec 30, 4:49 PM
Work Order: WO-01229139
Type: Preventive Maintenance
Priority: PSM
🚨 63.9 business days
Status: Ready for Release by Stephanie Ramen Apr 1, 12:18 PM
From: On Hold
To: Ready for Release
Duration in Previous: 91d 18h
🚨 63.0 business days
👷
2 Technician Assigned Jun 30, 10:13 AM
Technician Assigned → Status: Assigned
👷
Status: Assigned by Rhea Berry
From: Ready for Release
To: Assigned
Duration in Previous: 89d 21h
🗓️
2 Status: Scheduled Jun 30, 12:37 PM
Status: Scheduled → Dispatch Scheduled
📅
Dispatch Scheduled by Rhea Berry
Scheduled For: 2025-07-09T15:15:00.000+0000
⚠️ 7.0 business days
🔧
2 Status: Tech On Site Jul 9, 11:18 AM
Status: Tech On Site → 2x Labor Added
⏱️
2x Labor Added
Type: Labor, Travel
Status: Open
Qty: 0.33333333333333, 10
⏱️
2 Labor Added Jul 9, 11:54 AM
Labor Added → Status: Completed
✔️
Status: Completed by Alexis Vasquez
From: Tech On Site
To: Completed
Duration in Previous: 37m
🔄
Status: Reschedule by Rhea Berry Jul 9, 1:44 PM
From: Completed
To: Reschedule
Duration in Previous: 1h 48m
2.0 business days
Status: Ready for Release by Rhea Berry Jul 10, 11:02 PM
From: Reschedule
To: Ready for Release
Duration in Previous: 1d 9h
🚨 31.1 business days
👷
2 Status: Assigned Aug 22, 10:58 AM
Status: Assigned → Technician Assigned
👷
Technician Assigned by Rhea Berry
Technician: Mike Huffman
🗓️
2 Status: Scheduled Aug 22, 11:29 AM
Status: Scheduled → Dispatch Scheduled
📅
Dispatch Scheduled by Rhea Berry
Scheduled For: 2025-09-10T13:45:00.000+0000
🚨 13.0 business days
🔧
Status: Tech On Site by MICHAEL HUFFMAN Sep 10, 9:50 AM
From: Scheduled
To: Tech On Site
Duration in Previous: 18d 22h
⏱️
3x Labor Added Sep 10, 10:31 AM
Type: Labor, Travel
Status: Open
Qty: 0.5, 12
✔️
Status: Completed by MICHAEL HUFFMAN Sep 10, 10:36 AM
From: Tech On Site, Completed
To: Completed, Closed
Duration in Previous: 45m, 0m
📄
Status: Ready to Bill by Timothy Amburgey Sep 10, 10:52 AM
From: Closed
To: Ready to Bill
Duration in Previous: 15m
📨
Status: Invoice Pending by Timothy Amburgey Sep 10, 12:04 PM
From: Ready to Bill, Invoice Pending
To: Invoice Pending, Invoiced
Duration in Previous: 1h 11m, 0m
4.0 business days
🧾
Invoice Created Sep 15, 11:49 AM
Invoice Number: SM-240497

Bottlenecks

Scheduled
Duration: 6.9 business days (threshold: 2.0 business days)
Exceeded by 4.9 business days
Reschedule
Duration: 2.2 business days (threshold: 2.0 business days)
Exceeded by 1.3 business hours
Scheduled
Duration: 13.0 business days (threshold: 2.0 business days)
Exceeded by 11.0 business days

🔗 Related Artifacts

No related artifacts

ℹ️ Work Order Details

Status
Invoiced
Priority
PSM
Type
Preventive Maintenance
Branch
N/A
Technician
Mike Huffman
Scheduled
Sep 10, 9:45 AM
Created
Dec 30, 4:49 PM
Invoice #
SM-240497

Work Details (6)

Name Type Status Qty Amount Date
WL-02858679 Labor Open 0.33333333333333 $0.00 Jul 9, 11:21 AM
WL-02858681 Travel Open 10 $0.00 Jul 9, 11:21 AM
WL-02858724 Labor Open 1 $0.00 Jul 9, 11:54 AM
WL-02930882 Labor Open 0.5 $0.00 Sep 10, 10:31 AM
WL-02930883 Labor Open 0.5 $0.00 Sep 10, 10:31 AM
WL-02930884 Travel Open 12 $0.00 Sep 10, 10:31 AM