Last business day of December 2024 · Target: Dec 31, 2024
✗ SLA Missed (75 biz days late)
Active: 77 biz days
Paused: 100 biz days
🕐 Clock stopped: Tech Off Site (Sep 12, 2025)
63d
▶ Clock Running
Status: Created
Dec 30 → Apr 1, 2025
63 business days (counted)
Running total: 63 of ? biz days used
⏸100d
⏸ Clock Paused
Status: Ready for Release
Apr 1 → Aug 22, 2025
100 business days (not counted)
▶ Clock Running
Status: Assigned
Aug 22 → Aug 22, 2025
0 business days (counted)
Running total: 63 of ? biz days used
▶ Clock Running
Status: Scheduled
Aug 22 → Sep 11, 2025
13 business days (counted)
Running total: 76 of ? biz days used
▶ Clock Running
Status: Completed
Sep 11 → Sep 11, 2025
0 business days (counted)
Running total: 76 of ? biz days used
▶ Clock Running
Status: Closed
Sep 11 → Sep 11, 2025
0 business days (counted)
Running total: 76 of ? biz days used
▶ Clock Running
Status: Incomplete
Sep 11 → Sep 12, 2025
1 business day (counted)
Running total: 77 of ? biz days used
▶ Clock Running
Status: Scheduled
Sep 12 → Sep 12, 2025
0 business days (counted)
Running total: 77 of ? biz days used
Created: Dec 30, 2024Tech Off Site: Sep 12, 2025
Show SLA Clock Detail (8 periods)
Period
Status
Clock
Biz Days
Running Total
Dec 30 → Apr 1
Created
▶ Running
63
63
Apr 1 → Aug 22
Ready for Release
⏸ Paused
100
—
Aug 22 → Aug 22
Assigned
▶ Running
0
63
Aug 22 → Sep 11
Scheduled
▶ Running
13
76
Sep 11 → Sep 11
Completed
▶ Running
0
76
Sep 11 → Sep 11
Closed
▶ Running
0
76
Sep 11 → Sep 12
Incomplete
▶ Running
1
77
Sep 12 → Sep 12
Scheduled
▶ Running
0
77
Holding164.2d (excluded)
Coordinators14.2d
Field Work1.0d
Incomplete1.0d (excluded)
Billing0.2d
✗ SLA Missed
Holding(excluded from total)
164.2 days
Coordinators
14.2 days
Over SLA
Field Work
1.0 days
Incomplete(excluded from total)
1.0 days
Billing
0.2 days
Created: Dec 30, 2024
Due: Dec 31, 2025
Completed: Sep 13, 2025 (109 days early)
📅
177.3 daysTotal Age
⏱️
101.0d in Ready for ReleaseLongest Stage
🔄
12 transitionsStatus Changes
⚠️
12.0d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
3 linesWork Details
🏠
1 visitOn-Site Trips
📋
CoordinatorScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 429 days old
🚨
Primary Delay101.0 days stuck in "Ready for Release"
⏱️
Total Delay12.0 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
63.3d
Ready for Release
101.0d
Assigned
0.0d / 0.5d SLA
Scheduled
14.2d / 2.0d SLA
Completed
0.0d / 1.0d SLA
Closed
1.0d / 1.0d SLA
Incomplete
1.0d
Tech Off Site
1.0d / 2.0d SLA
Ready to Bill
0.2d / 1.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
9-12-25 dt
wo was completed today. i accidently completed this work order yesterday by accident. i clicked on this wo by accident. Matt reopened yesterday. i deleted all entries and i completed it today. on its originally scheduled day
🔧Work Performed
Upon arrival, unit up and running. LEDs illuminated. Top and bottom screens display properly. Seat lock functioning
Performed and completed preventative maintenance procedures on this unit. Unit passes functional testing and has been returned to service.
🔍Technician Findings
Upon arrival, unit up and running. LEDs illuminated. Top and bottom screens display properly. Seat lock functioning
Performed and completed preventative maintenance procedures on this unit. Unit passes functional testing and has been returned to service.
⚠️Problem Description
Please Perform a PM on this Kiosk and attach all required photos from Checklist Regardless if a PM was completed or not a Checklist and photos are required as well as a signed field service report for every work order If a follow up is needed: Confirm with Tech support, select New issue, enter in the troubleshooting performed and part needed for the follow up in the follow up notes field Trunk stock work order: email dispatch@emsar.com with current work order # and the description of the repair that is required to be performed prior to PM completion (Example LED lights, bamboo seat replacement, Leveler replacement etc. all parts that can be found in your trunk stock ) Link to Work Instructions & Checklist on last page: SZZT (Higi Green) https://emsar-portal1.sharepoint.com/SOPs%20and%20Work%20Instructions/Higi%20&%20Legacy%20Kiosk%20Group/Higi%20Green/WI-ST-310%20Higi%20Green%20Preventative%20Maintenance%20009%20DCR652.pdf