📍 CVS - CVS-02786 — 255 Norht Mclean Boulevard, South Elgin IL, 60177
Jan 2, 2025 → Oct 9, 2025
✅ Completed
PSM
SLA Clock
Last business day of January 2025 · Target: Jan 31, 2025
✗ SLA Missed (97 biz days late)
Active: 118 biz days
Paused: 76 biz days
🕐 Clock stopped: Completed (Oct 9, 2025)
61d
▶ Clock Running
Status: Created
Jan 2 → Apr 1, 2025
61 business days (counted)
Running total: 61 of ? biz days used
⏸59d
⏸ Clock Paused
Status: Ready for Release
Apr 1 → Jun 25, 2025
59 business days (not counted)
▶ Clock Running
Status: Assigned
Jun 25 → Jun 25, 2025
0 business days (counted)
Running total: 61 of ? biz days used
▶ Clock Running
Status: Scheduled
Jun 25 → Jul 17, 2025
15 business days (counted)
Running total: 76 of ? biz days used
32d
▶ Clock Running
Status: Incomplete
Jul 17 → Sep 2, 2025
32 business days (counted)
Running total: 108 of ? biz days used
⏸17d
⏸ Clock Paused
Status: Ready for Release
Sep 2 → Sep 25, 2025
17 business days (not counted)
▶ Clock Running
Status: Scheduled
Sep 25 → Sep 25, 2025
0 business days (counted)
Running total: 108 of ? biz days used
▶ Clock Running
Status: Entered
Sep 25 → Sep 25, 2025
0 business days (counted)
Running total: 108 of ? biz days used
▶ Clock Running
Status: Assigned
Sep 25 → Sep 25, 2025
0 business days (counted)
Running total: 108 of ? biz days used
▶ Clock Running
Status: Scheduled
Sep 25 → Oct 9, 2025
10 business days (counted)
Running total: 118 of ? biz days used
▶ Clock Running
Status: Tech On Site
Oct 9 → Oct 9, 2025
0 business days (counted)
Running total: 118 of ? biz days used
Created: Jan 2, 2025Completed: Oct 9, 2025
Show SLA Clock Detail (11 periods)
Period
Status
Clock
Biz Days
Running Total
Jan 2 → Apr 1
Created
▶ Running
61
61
Apr 1 → Jun 25
Ready for Release
⏸ Paused
59
—
Jun 25 → Jun 25
Assigned
▶ Running
0
61
Jun 25 → Jul 17
Scheduled
▶ Running
15
76
Jul 17 → Sep 2
Incomplete
▶ Running
32
108
Sep 2 → Sep 25
Ready for Release
⏸ Paused
17
—
Sep 25 → Sep 25
Scheduled
▶ Running
0
108
Sep 25 → Sep 25
Entered
▶ Running
0
108
Sep 25 → Sep 25
Assigned
▶ Running
0
108
Sep 25 → Oct 9
Scheduled
▶ Running
10
118
Oct 9 → Oct 9
Tech On Site
▶ Running
0
118
Holding139.3d (excluded)
Coordinators26.8d
Field Work0.2d
Incomplete33.0d (excluded)
Billing16.8d
✗ SLA Missed
Holding(excluded from total)
139.3 days
Coordinators
26.8 days
Over SLA
Field Work
0.2 days
Incomplete(excluded from total)
33.0 days
Billing
16.8 days
Over SLA
Created: Jan 2, 2025
Due: Dec 31, 2025
Completed: Oct 9, 2025 (83 days early)
📅
194.5 daysTotal Age
⏱️
61.5d in On HoldLongest Stage
🔄
13 transitionsStatus Changes
⚠️
38.1d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
3 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 426 days old
🚨
Primary Delay61.5 days stuck in "On Hold"
⏱️
Total Delay38.1 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
On Hold
61.5d
Ready for Release
77.9d
Assigned
0.7d / 0.5d SLA
Scheduled
26.2d / 2.0d SLA
Incomplete
33.0d
Tech On Site
0.2d / 1.0d SLA
Closed
0.2d / 1.0d SLA
Ready to Bill
16.8d / 1.0d SLA
Invoice Pending
0.0d / 2.0d SLA
💬 Activities, Notes & Communications
🔧Work Performed
10/9/2025 Mike Huffman. Completed the PM, field service report and obtained signature.
🔍Technician Findings
Kiosk does not show signs of customer damage.
Kiosk is fully operational. Yes
Was the kiosk unplugged on arrival? No
⚠️Problem Description
Please Perform PM: PM Checklist can be found as a link in the work order under WO actions
If Kiosk is not on the Sales floor request to speak to a manager to find out if kiosk is being stored in the back room or if it was disposed. Offer to help bring the kiosk to the salesfloor or advise that EMSAR can replace a disposed kiosk. If store does not want to bring the kiosk out of storage or if kiosk was disposed, close out work order with Repair code '37 Store intervention required' and document who you spoke with and outcome of conversation. Labor line shall be a trip charge.
***Important: Please make sure to document if kiosk is disposed or in storage***
If kiosk fails a PM, checklist is still required to be completed. Please use Code 35 - Follow up needed and detail in the Tech Findings, Work Performed and Final condition the result and cause for a follow up. Close out the work order. Dispatch will create a follow up repair work order to send parts.