📍 UNIVERSITY OF CINCINNATI MEDICAL CENTER — 331 ALBERT SABIN WAY, CINCINNATI OH, 45229
Jun 19, 2025 → Oct 29, 2025
✅ Completed
PC
SLA Clock
Per client agreement · Target: Jan 31, 2026
✓ SLA Met (61 biz days early)
Active: 34 biz days
Paused: 57 biz days
🕐 Clock stopped: Completed (Oct 29, 2025)
▶ Clock Running
Status: Created
Jun 19 → Jun 19, 2025
0 business days (counted)
Running total: 0 of ? biz days used
⏸9d
⏸ Clock Paused
Status: Ready for Release
Jun 19 → Jul 2, 2025
9 business days (not counted)
28d
▶ Clock Running
Status: On Hold
Jul 2 → Aug 12, 2025
28 business days (counted)
Running total: 28 of ? biz days used
⏸48d
⏸ Clock Paused
Status: Ready for Release
Aug 12 → Oct 21, 2025
48 business days (not counted)
▶ Clock Running
Status: Ready for Scheduling
Oct 21 → Oct 21, 2025
0 business days (counted)
Running total: 28 of ? biz days used
▶ Clock Running
Status: Scheduled
Oct 21 → Oct 29, 2025
6 business days (counted)
Running total: 34 of ? biz days used
▶ Clock Running
Status: Tech On Site
Oct 29 → Oct 29, 2025
0 business days (counted)
Running total: 34 of ? biz days used
Created: Jun 19, 2025Completed: Oct 29, 2025
Show SLA Clock Detail (7 periods)
Period
Status
Clock
Biz Days
Running Total
Jun 19 → Jun 19
Created
▶ Running
0
0
Jun 19 → Jul 2
Ready for Release
⏸ Paused
9
—
Jul 2 → Aug 12
On Hold
▶ Running
28
28
Aug 12 → Oct 21
Ready for Release
⏸ Paused
48
—
Oct 21 → Oct 21
Ready for Scheduling
▶ Running
0
28
Oct 21 → Oct 29
Scheduled
▶ Running
6
34
Oct 29 → Oct 29
Tech On Site
▶ Running
0
34
Holding86.4d (excluded)
Coordinators7.1d
Field Work0.2d
Billing2.9d
✓ SLA Met
Holding(excluded from total)
86.4 days
Coordinators
7.1 days
Over SLA
Field Work
0.2 days
Billing
2.9 days
Over SLA
Created: Jun 19, 2025
Due: Jan 31, 2026
Completed: Oct 29, 2025 (94 days early)
📅
91.0 daysTotal Age
⏱️
49.0d in Ready for ReleaseLongest Stage
🔄
10 transitionsStatus Changes
⚠️
8.7d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
6 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with minor delays
Invoiced • 258 days old
🚨
Primary Delay49.0 days stuck in "Ready for Release"
⏱️
Total Delay8.7 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.0d / 0.5d SLA
Ready for Release
58.0d
On Hold
28.4d
Ready for Scheduling
0.3d / 1.0d SLA
Scheduled
6.8d / 2.0d SLA
Tech On Site
0.2d / 1.0d SLA
Closed
3.0d / 1.0d SLA
Ready to Bill
2.9d / 1.0d SLA
Invoice Pending
0.0d / 2.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
10/21/2025 DMalloy - Emailed customer advising that FSE Eric can be onsite on next week Monday 10/27/2025 for the 21 devices.
michael.galloway@gehealthcare.com
10/21/2025 MK rcvd email from Mike Galloway, confirm devices. .. 10/20/2025 mklose called 1-262-794-7501; Mike Galloway. michael.galloway@gehealthcare.com. email Mike and he wiill reach out tomorrow, with a list of where all devices are and wil schedule. 10/20/2025 mklose called 1-859-274-6342 Ryan Mullins, ryan.mullins1@gehealthcare.com, LVM 10/15/2025 mklose emailed Joseph; Joseph.Hinton@gehealthcare.com, and Tyler; tyler.martinez@gehealthcare.com ... 09/03/2025 RFosbury - rec'd email from Steve stating he no longer supports for this region, he looped in ASLs Hinton, Joseph and Martinez, Tyler ... 09/03/2025 RFosbury called Steve Steinhaus, Field Support Spec GEHC @ 414-530-8334, left VM and followed up with email to Steve.steinhaus@gehealthcare.com.
🔧Work Performed
"Template Name:
Template Description:
Problem Found:
Action Taken: Completed FMI 78101 by installing SW Version R5.1 and communicated with customer to scrap previous software versions.
Verification Test: Performed Probe and Connectors Checks for all probes. Confirmed all probes pass. Completed all Peripheral Checks-system passed. Completed full system diagnostics-system passed.
Equipment passed all required tests and has been returned to the customer fully functional."
🔍Technician Findings
78101
⚠️Problem Description
FMI 78101H: Venue Fit Thermal Event due to battery Purpose: Each affected system will have a SW Version R5.0.5 update installed. FMI Type: Mandatory Recall FMI For code 2, 3, 4 and 5 closures, please reach out to FMI admin team at TCS.FMIAdmin@gehealthcare.com or 8668836784 – OPT. 5 for assistance in closing and correct objective evidence attachment to Activity/SR.
📄Description
GE Healthcare - Venue Fit Ultrasound
📞Call Description
FMI 78101
📧
Live Call_Followed Up With Email
Completed Oct 20, 2025
10/20/2025 mklose called 1-262-794-7501; Mike Galloway. michael.galloway@gehealthcare.com. email Mike and he wiill reach out tomorrow, with a list of where all devices are and wil schedule.
📞
Live Call_ Left Message
Completed Oct 20, 2025
10/20/2025 mklose called 1-859-274-6342 Ryan Mullins, ryan.mullins1@gehealthcare.com, LVM
JPG
VFE000270 SERIAL #
Oct 29, 2025
PDF
VFE000270
Oct 29, 2025
JPG
VFE000270 WORKLIST
Oct 29, 2025
JPG
VFE000270 BATTERIES
Oct 29, 2025
Timeline
📋
Work Order Created Jun 19, 2:26 PM
Work Order:WO-01280889
Type:FCO
Priority:PC
✅
Status: Ready for Release by Allison BelyeaJun 19, 3:09 PM
From:Entered
To:Ready for Release
Duration in Previous:43m
⚠️9.0 business days
⏸️
Status: On Hold by Allison BelyeaJul 2, 4:41 PM
From:Ready for Release
To:On Hold
Duration in Previous:13d 1h
🚨28.9 business days
✅
Status: Ready for Release by Allison BelyeaAug 12, 11:12 AM
From:On Hold
To:Ready for Release
Duration in Previous:40d 18h
🚨49.0 business days
📅
Status: Ready for Scheduling by Megan KloseOct 21, 11:27 AM