Created: Jun 19, 2025
Due: Jan 31, 2026
Completed: Sep 30, 2025 (123 days early)
📅
71.0 daysTotal Age
⏱️
48.6d in Ready for SchedulingLongest Stage
🔄
13 transitionsStatus Changes
⚠️
48.9d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
8 linesWork Details
🏠
1 visitOn-Site Trips
👤
Self-ScheduledScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 258 days old
🚨
Primary Delay48.6 days stuck in "Ready for Scheduling"
⏱️
Total Delay48.9 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.0d / 0.5d SLA
Ready for Release
23.0d
Ready for Scheduling
48.6d / 1.0d SLA
Scheduled
0.0d / 2.0d SLA
Tech On Site
0.5d / 1.0d SLA
Tech Off Site
0.2d / 2.0d SLA
Completed
0.0d / 1.0d SLA
Closed
1.4d / 1.0d SLA
07e-Partial Project
0.0d
Ready to Bill
2.0d / 1.0d SLA
Invoice Pending
2.6d / 2.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
07/23/2025 RArnold - Sai confirmed devices. Scheduling Shady for 07/29. WOs on demand.
07/23/2025 RArnold - Called 551-352-9187 for Sai Gullapalli. Sending email with SN#. No credentialing. Address confirmed He will be POC. saicharan.gullapalli@crothall.com
🔧Work Performed
"Template Name:
Template Description:
Problem Found:
Action Taken: “Completed FMI 78101 by installing SW Version R4.4.3 or R4.5 and communicated with customer to scrap previous software versions”.
Verification Test: “Performed Probe and Connectors Checks for all probes. Confirmed all probes pass. Completed all Peripheral Checks-system passed. Completed full system diagnostics-system passed.
Equipment passed all required tests and has been returned to the customer fully functional”.
Template Name:
Template Description:
Problem Found:
Action Taken: “Completed FMI 78101 by installing new supplied batteries / Batteries installed by
customer and dispose of old batteries according to local regulation”.
Verification Test: “Performed battery charging test - verified after 10 minutes, the scan time increased. Completed full system diagnostics-system passed. Equipment passed all required tests and has been returned to the customer fully functional”."
🔍Technician Findings
"Template Name:
Template Description:
Problem Found:
Action Taken: “Completed FMI 78101 by installing SW Version R4.4.3 or R4.5 and communicated with customer to scrap previous software versions”.
Verification Test: “Performed Probe and Connectors Checks for all probes. Confirmed all probes pass. Completed all Peripheral Checks-system passed. Completed full system diagnostics-system passed.
Equipment passed all required tests and has been returned to the customer fully functional”.
⚠️Problem Description
FMI 78101D: Venue Go Thermal Event due to battery Purpose: Each affected system will have a SW Version R4.4.3 update installed. FMI Type: Mandatory Recall FMI For code 2, 3, 4 and 5 closures, please reach out to FMI admin team at TCS.FMIAdmin@gehealthcare.com or 8668836784 – OPT. 5 for assistance in closing and correct objective evidence attachment to Activity/SR.
📄Description
GE Healthcare - Venue Go Ultrasound
📞Call Description
FMI 78101
📅
WO-01283040 - FCO - Venue Go Ultrasound - BRONX - NYC HEALTH + HOSPITALS JACOBI
Sep 30, 2025 8:00am – 5:00pm
Work Order: WO-01283040
Account: GE Healthcare FMI
Customer Case Number: 1-554880192341, 1-554908087330
Location: NYC HEALTH + HOSPITALS JACOBI
Address: 1400 PELHAM PKWY S, BRONX, NY 10461
Manufacturer: GE Healthcare
Model #: Venue Go Ultrasound
Serial #: VGD001837
Contact Name: Sai Gullapalli
Conta
JPG
VGD001837_Software Update
Sep 30, 2025
JPG
VGD001837_Product Label
Sep 30, 2025
JPG
VGD001837_Battery Replacement
Sep 30, 2025
Timeline
📋
Work Order Created Jun 19, 2:28 PM
Work Order:WO-01283040
Type:FCO
Priority:PC
✅
Status: Ready for Release by Allison BelyeaJun 19, 3:13 PM
From:Entered
To:Ready for Release
Duration in Previous:45m
🚨23.0 business days
📅
Status: Ready for Scheduling by Rebecca ArnoldJul 23, 3:15 PM
From:Ready for Release
To:Ready for Scheduling
Duration in Previous:34d 0h
🚨49.0 business days
👷
▶
4
Technician Assigned Sep 30, 10:55 AM
Technician Assigned → Status: Assigned → Dispatch Scheduled → Status: Tech On Site
👷
Status: Assigned by Cristina Everetts
From:Ready for Scheduling, Assigned
To:Assigned, Scheduled
Duration in Previous:68d 19h, 0m
📅
Dispatch Scheduled by Cristina Everetts
Scheduled For:2025-09-30T12:00:00.000+0000
🔧
Status: Tech On Site by Israel Martell
From:Scheduled
To:Tech On Site
Duration in Previous:2m
⏱️
2x Labor Added Sep 30, 11:55 AM
Type:Labor
Status:Open
Qty:1.5, 2.5
🚗
3x Travel Added Sep 30, 12:08 PM
Type:Travel, Expenses
Status:Open
Qty:21, 20
⏱️
▶
2
2x Labor Added Sep 30, 3:00 PM
2x Labor Added → Status: Tech Off Site
🚗
Status: Tech Off Site by Israel Martell
From:Tech On Site
To:Tech Off Site
Duration in Previous:4h 4m
✔️
▶
2
Status: Completed Sep 30, 4:56 PM
Status: Completed → Status: Closed
🏁
Status: Closed by Israel Martell
From:Completed
To:Closed
Duration in Previous:1m
⏱️
▶
3
Labor Added Oct 1, 9:19 AM
Labor Added → Status: 07e-Partial Project → Status: Ready to Bill
📋
Status: 07e-Partial Project by Timothy Amburgey
From:Closed
To:07e-Partial Project
Duration in Previous:16h 23m
📄
Status: Ready to Bill by Timothy Amburgey
From:07e-Partial Project
To:Ready to Bill
Duration in Previous:1m
📨
Status: Invoice Pending by Timothy AmburgeyOct 1, 3:06 PM
From:Ready to Bill
To:Invoice Pending
Duration in Previous:5h 43m
⏳3.0 business days
📄
Status: Ready to Bill by Micah PetersOct 3, 5:22 PM
From:Invoice Pending
To:Ready to Bill
Duration in Previous:2d 2h
⏳1.8 business days
📨
Status: Invoice Pending by Yecenia CamposOct 6, 12:55 PM
From:Ready to Bill
To:Invoice Pending
Duration in Previous:2d 19h
💰
Status: Invoiced by Yecenia CamposOct 6, 1:12 PM
From:Invoice Pending
To:Invoiced
Duration in Previous:16m
⏳4.0 business days
🧾
Invoice Created Oct 9, 2:36 PM
Invoice Number:SM-242983
Bottlenecks
Ready for Scheduling
Duration: 48.6 business days (threshold: 1.0 business days)
Exceeded by 47.6 business days
Closed
Duration: 1.4 business days (threshold: 1.0 business days)
Exceeded by 3.0 business hours
Invoice Pending
Duration: 2.6 business days (threshold: 2.0 business days)
Exceeded by 4.9 business hours
Ready to Bill
Duration: 1.3 business days (threshold: 1.0 business days)