📍 CHRISTIANA HOSPITAL — 4755 OGLETOWN STANTON RD, NEWARK DE, 19718
Sep 4, 2025 → Jan 7, 2026
✅ Completed
PC
SLA Clock
Per client agreement · Target: Nov 30, 2025
✗ SLA Missed (9 biz days late)
Active: 66 biz days
Paused: 17 biz days
🕐 Clock stopped: Completed (Jan 7, 2026)
▶ Clock Running
Status: Created
Sep 4 → Sep 4, 2025
0 business days (counted)
Running total: 0 of ? biz days used
⏸17d
⏸ Clock Paused
Status: Ready for Release
Sep 4 → Sep 29, 2025
17 business days (not counted)
15d
▶ Clock Running
Status: Scheduled
Sep 29 → Oct 21, 2025
15 business days (counted)
Running total: 15 of ? biz days used
▶ Clock Running
Status: Entered
Oct 21 → Oct 28, 2025
5 business days (counted)
Running total: 20 of ? biz days used
46d
▶ Clock Running
Status: Assigned
Oct 28 → Jan 7, 2026
46 business days (counted)
Running total: 66 of ? biz days used
▶ Clock Running
Status: Scheduled
Jan 7 → Jan 7, 2026
0 business days (counted)
Running total: 66 of ? biz days used
Created: Sep 4, 2025Completed: Jan 7, 2026
Show SLA Clock Detail (6 periods)
Period
Status
Clock
Biz Days
Running Total
Sep 4 → Sep 4
Created
▶ Running
0
0
Sep 4 → Sep 29
Ready for Release
⏸ Paused
17
—
Sep 29 → Oct 21
Scheduled
▶ Running
15
15
Oct 21 → Oct 28
Entered
▶ Running
5
20
Oct 28 → Jan 7
Assigned
▶ Running
46
66
Jan 7 → Jan 7
Scheduled
▶ Running
0
66
Dispatch6.0d
Holding18.0d (excluded)
Coordinators63.2d
Billing16.1d
✗ SLA Missed
Dispatch
6.0 days
Over SLA
Holding(excluded from total)
18.0 days
Coordinators
63.2 days
Over SLA
Billing
16.1 days
Over SLA
Created: Sep 4, 2025
Due: Nov 30, 2025
Completed: Jan 7, 2026 (37 days late)
📅
84.0 daysTotal Age
⏱️
47.0d in AssignedLongest Stage
🔄
18 transitionsStatus Changes
⚠️
81.4d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
5 linesWork Details
🏠
1 visitOn-Site Trips
📋
CoordinatorScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 181 days old
🚨
Primary Delay47.0 days stuck in "Assigned"
⏱️
Total Delay81.4 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
6.0d / 0.5d SLA
Ready for Release
18.0d
Scheduled
16.2d / 2.0d SLA
Assigned
47.0d / 0.5d SLA
Closed
6.4d / 1.0d SLA
Ready to Bill
16.0d / 1.0d SLA
Billing Review
0.0d / 2.0d SLA
Invoice Pending
0.0d / 2.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
10/28/2025 Cever email sent to Carr, Lisa R to confirm new list of inventory and schedule FSE back onsite
🔧Work Performed
Template Name: FMI32097_Code 1_inspect.
Template Description: FMI32097_Code 1_inspect.
Problem Found: FMI32097_Heater door inspection.
Action Taken: FMI 32097 completed. Inspected the Heater doors
and confirmed screws tightened to the specification.
Verification Test:
1. Verified the canopy moves smoothly.
2. Verified transition mode message is not present.
3. Verified doors close smoothly.
4. Verified corner pins are aligned.
5. Verified no alarms.
The device has passed all tests and is ready for customer use.
🔍Technician Findings
good working conditions
⚠️Problem Description
FMI 32097:- Inspection of heater door screws for Giraffe OmniBed and Giraffe OmniBed Carestation Purpose:- Certain Giraffe OmniBed and Giraffe OmniBed Carestation may have defective heater doors due to improper torquing of heater door screws. FMI Type: Mandatory Recall FMI For code 2, 3, 4 and 5 closures, please reach out to FMI admin team at tcs.fmiadmins@gehealthcare.com or 8668836784 – OPT. 5 for assistance in closing and correct objective evidence attachment to Activity/SR.
Work Order: WO-01301329
Account: GE Healthcare FMI
Customer Case Number: 1-555654318755
Location: CHRISTIANA HOSPITAL
Address: 4755 OGLETOWN STANTON RD, NEWARK, DE 19718
Manufacturer:
Model #: Giraffe OmniBed
Serial #: HDGR53418
Contact Name: Lisa Carr
Contact Phone: (302)733-3457/ (302)593-4751 (c
JPG
HDGR53419_Heater door closed
Jan 7, 2026
JPG
HDGR53419_Right screw
Jan 7, 2026
JPG
HDGR53419_Giraffe Omnibed
Jan 7, 2026
JPG
HDGR53419_Heater door open
Jan 7, 2026
JPG
HDGR53419_left screw
Jan 7, 2026
PDF
FMI Completion Certification Report_HDGR53418
Jan 7, 2026
Timeline
📋
Work Order Created Sep 4, 9:33 AM
Work Order:WO-01301329
Type:FCO
Priority:PC
✅
Status: Ready for Release by Allison BelyeaSep 4, 9:55 AM