📍 UC HEALTH WEST CHESTER HOSPITAL — 7700 UNIVERSITY DR, West Chester OH, 45069
Nov 6, 2025 → Nov 24, 2025
✅ Completed
P5
SLA Clock
5 business days from creation · Target: Nov 14, 2025
✗ SLA Missed
Active: 4 biz days
Paused: 8 biz days
Budget: 5 biz days
🕐 Clock stopped: Completed (Nov 25, 2025)
SLA Target
▶ Clock Running
Status: Created
Nov 6 → Nov 6, 2025
0 business days (counted)
Running total: 0 of 5 biz days used
▶ Clock Running
Status: Ready for Scheduling
Nov 6 → Nov 7, 2025
1 business day (counted)
Running total: 1 of 5 biz days used
1d
▶ Clock Running
Status: Assigned
Nov 7 → Nov 10, 2025
1 business day (counted)
Running total: 2 of 5 biz days used
⏸8d
⏸ Clock Paused
Status: Awaiting Parts
Nov 10 → Nov 21, 2025
8 business days (not counted)
1d
▶ Clock Running
Status: Reschedule
Nov 21 → Nov 24, 2025
1 business day (counted)
Running total: 3 of 5 biz days used
▶ Clock Running
Status: Tech On Site
Nov 24 → Nov 25, 2025
1 business day (counted)
Running total: 4 of 5 biz days used
Created: Nov 6, 2025Completed: Nov 25, 2025
Business Days Used4 / 5
05d budget
Show SLA Clock Detail (6 periods)
Period
Status
Clock
Biz Days
Running Total
Nov 6 → Nov 6
Created
▶ Running
0
0 / 5
Nov 6 → Nov 7
Ready for Scheduling
▶ Running
1
1 / 5
Nov 7 → Nov 10
Assigned
▶ Running
1
2 / 5
Nov 10 → Nov 21
Awaiting Parts
⏸ Paused
8
—
Nov 21 → Nov 24
Reschedule
▶ Running
1
3 / 5
Nov 24 → Nov 25
Tech On Site
▶ Running
1
4 / 5
Dispatch0.0d
Material Management8.5d
Coordinators3.8d
Field Work1.1d
Billing0.2d
✗ SLA Missed
Dispatch
0.0 days
Material Management
8.5 days
Over SLA
Coordinators
3.8 days
Over SLA
Field Work
1.1 days
Over SLA
Billing
0.2 days
Created: Nov 6, 2025
Due: Nov 13, 2025
Completed: Nov 25, 2025 (11 days late)
📅
11.9 daysTotal Age
⏱️
8.5d in Awaiting PartsLongest Stage
🔄
8 transitionsStatus Changes
⚠️
6.5d overTotal Delay
📦
1 orders, 0 quotesParts & Quotes
📝
6 linesWork Details
🏠
2 visitsOn-Site Trips
👤
Self-ScheduledScheduling
🔄
2 On-Site Visits
(1 reschedule)
2 on-site visits — follow-up trip required
👤 Self-scheduled by Franco Jackson — scheduling delays attributed to technician, not coordinators
Visit 1Nov 4, 2025
Visit 2Nov 24, 2025
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with minor delays
Invoiced • 118 days old
🚨
Primary Delay8.5 days stuck in "Awaiting Parts"
⏱️
Total Delay6.5 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.0d / 0.5d SLA
Ready for Scheduling
0.3d / 1.0d SLA
Assigned
1.5d / 0.5d SLA
Awaiting Parts
8.5d / 3.0d SLA
Reschedule
2.0d / 2.0d SLA
Tech On Site
1.1d / 1.0d SLA
Closed
1.0d / 1.0d SLA
Ready to Bill
0.2d / 1.0d SLA
💬 Activities, Notes & Communications
🔧Work Performed
4nov2025 fjackson checked all hoses and connections and secure, tried running P&V and ran for a minute then got a blower error 0xa0c5 and error 0xa0c8, followed troubleshooting steps in service manual and issue persist, suggest blower needs ordered
24nov2025 fjackson replaced blower and verified P&V function working, checked all functions and working ok, returned to floor
🔍Technician Findings
P&V not working
⚠️Problem Description
troubleshooting for bed reported P&V not working
Jackson, Robert
📄Description
Bed, Electric
Timeline
📋
▶
2
Work Order Created Nov 6, 4:25 PM
Work Order Created → Status: Ready for Scheduling
📅
Status: Ready for Scheduling by Sherry Reich
From:Entered
To:Ready for Scheduling
Duration in Previous:0m
👷
▶
2
Technician Assigned Nov 6, 7:08 PM
Technician Assigned → Status: Assigned
👷
Status: Assigned by Charles Ramen
From:Ready for Scheduling
To:Assigned
Duration in Previous:2h 41m
⏳1.6 business days
⏱️
3x Labor Added Nov 9, 9:42 PM
Type:Labor, Travel
Status:Open
Qty:1, 0.5, 22
📦
▶
2
Parts Requested Nov 9, 10:38 PM
Parts Requested → Status: Awaiting Parts
📦
Status: Awaiting Parts by Robert Jackson
From:Assigned
To:Awaiting Parts
Duration in Previous:3d 3h
⚠️8.0 business days
🔩
▶
2
2x Parts Added Nov 20, 11:07 PM
2x Parts Added → Status: Reschedule
🔄
Status: Reschedule by Keith Fricke
From:Awaiting Parts
To:Reschedule
Duration in Previous:11d 0h
⏳2.1 business days
🔧
Status: Tech On Site by Robert JacksonNov 24, 3:01 PM
From:Reschedule
To:Tech On Site
Duration in Previous:3d 15h
⏱️
▶
2
Labor Added Nov 24, 11:29 PM
Labor Added → Status: Completed
✔️
Status: Completed by Robert Jackson
From:Tech On Site, Completed
To:Completed, Closed
Duration in Previous:8h 28m, 0m
📄
Status: Ready to Bill by Hannah ShawNov 25, 2:12 PM
From:Closed
To:Ready to Bill
Duration in Previous:14h 42m
📨
Status: Invoice Pending by Hannah ShawNov 25, 3:53 PM
From:Ready to Bill, Invoice Pending
To:Invoice Pending, Invoiced
Duration in Previous:1h 40m
⏳3.0 business days
🧾
Invoice Created Dec 1, 12:33 PM
Invoice Number:SM-247579
Bottlenecks
Assigned
Duration: 1.5 business days (threshold: 4.0 business hours)
Exceeded by 7.6 business hours
Awaiting Parts
Duration: 8.5 business days (threshold: 3.0 business days)
Exceeded by 5.5 business days
Tech On Site
Duration: 1.1 business days (threshold: 1.0 business days)