Work Order 360 View

Detailed work order timeline, KPIs, and analysis

← WO Overview

WO-01325493 ↗ ServiceMax

GE Healthcare FMI • FCO • PC

📍 HAYS SURGERY CENTER — 135 BUNTON CREEK RD STE 200, KYLE TX, 78640

Dec 12, 2025 → Mar 4, 2026

✅ Completed
PC
SLA Clock
Per client agreement · Target: Feb 28, 2026
✗ SLA Missed
Active: 7 biz days
Paused: 48 biz days
🕐 Clock stopped: Completed (Mar 5, 2026)
▶ Clock Running
Status: Created
Dec 12 → Dec 15, 2025
1 business day (counted)
Running total: 1 of ? biz days used
⏸48d
⏸ Clock Paused
Status: Ready for Release
Dec 15 → Feb 25, 2026
48 business days (not counted)
▶ Clock Running
Status: Scheduled
Feb 25 → Mar 3, 2026
4 business days (counted)
Running total: 5 of ? biz days used
▶ Clock Running
Status: Tech On Site
Mar 3 → Mar 5, 2026
2 business days (counted)
Running total: 7 of ? biz days used
Created: Dec 12, 2025 Completed: Mar 5, 2026
Show SLA Clock Detail (4 periods)
Period Status Clock Biz Days Running Total
Dec 12 → Dec 15 Created ▶ Running 1 1
Dec 15 → Feb 25 Ready for Release ⏸ Paused 48
Feb 25 → Mar 3 Scheduled ▶ Running 4 5
Mar 3 → Mar 5 Tech On Site ▶ Running 2 7
Dispatch 2.0d
Holding 48.8d (excluded)
Coordinators 4.8d
Field Work 1.5d
✗ SLA Missed
Dispatch
2.0 days
Over SLA
Holding (excluded from total)
48.8 days
Coordinators
4.8 days
Over SLA
Field Work
1.5 days
Over SLA
Created: Dec 12, 2025 Due: Feb 28, 2026 Completed: Mar 5, 2026 (4 days late)
📅
55.5 days Total Age
⏱️
48.8d in Ready for Release Longest Stage
🔄
4 transitions Status Changes
⚠️
4.7d over Total Delay
📦
0 orders, 0 quotes Parts & Quotes
📝
7 lines Work Details
🏠
1 visit On-Site Trips
👤
Self-Scheduled Scheduling

AI Analysis

Powered by OpenAI
Generating AI analysis...
Completed with minor delays
Closed • 82 days old
🚨
Primary Delay 48.8 days stuck in "Ready for Release"
⏱️
Total Delay 4.7 business days over SLA thresholds

SLA vs Actual Time by Status

Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
2.0d / 0.5d SLA
Ready for Release
48.8d
Scheduled
4.8d / 2.0d SLA
Tech On Site
1.5d / 1.0d SLA

💬 Activities, Notes & Communications

🔒 Internal CSA Notes

02/25/2026 mklose dispatch Philmon - walk in

02/23/2026 MHamersley - called 512-504-0202, Office is already closed for the day; call went to VM/LM


Venue Fit Ultrasound VFC000158

🔧 Work Performed
"Template Name: Template Description: Problem Found: Action Taken: “Completed FMI 78101 by installing SW Version R4.4.3 and communicated with customer to scrap previous software versions”. Verification Test: “Performed Probe and Connectors Checks for all probes. Confirmed all probes pass. Completed all Peripheral Checks-system passed. Completed full system diagnostics-system passed. Equipment passed all required tests and has been returned to the customer fully functional”. Template Name: Template Description: Problem Found: Action Taken: “Completed FMI 78101 by installing new supplied batteries / Batteries installed by customer and dispose of old batteries according to local regulation”. Verification Test: “Performed battery charging test - verified after 10 minutes, the scan time increased. Completed full system diagnostics-system passed. Equipment passed all required tests and has been returned to the customer fully functional”"
🔍 Technician Findings
"Template Name: Template Description: Problem Found: Action Taken: “Completed FMI 78101 by installing SW Version R4.4.3 and communicated with customer to scrap previous software versions”. Verification Test: “Performed Probe and Connectors Checks for all probes. Confirmed all probes pass. Completed all Peripheral Checks-system passed. Completed full system diagnostics-system passed. Equipment passed all required tests and has been returned to the customer fully functional”. Template Name: Template Description: Problem Found: Action Taken: “Completed FMI 78101 by installing new supplied batteries / Batteries installed by customer and dispose of old batteries according to local regulation”. Verification Test: “Performed battery charging test - verified after 10 minutes, the scan time increased. Completed full system diagnostics-system passed. Equipment passed all required tests and has been returned to the customer fully functional”"
⚠️ Problem Description
FMI 78101E: Venue Fit Thermal Event due to battery Purpose: Each affected system will have a SW Version R4.5 update installed. FMI Type: Mandatory Recall FMI For code 2, 3, 4 and 5 closures, please reach out to FMI admin team at TCS.FMIAdmin@gehealthcare.com or 8668836784 – OPT. 5 for assistance in closing and correct objective evidence attachment to Activity/SR.
📄 Description
GE Healthcare - Venue Fit Ultrasound
📞 Call Description
FMI 78101

Timeline

📋
Work Order Created Dec 12, 11:06 AM
Work Order: WO-01325493
Type: FCO
Priority: PC
2.0 business days
Status: Ready for Release by Mandy Newman Dec 15, 12:16 PM
From: Entered
To: Ready for Release
Duration in Previous: 3d 1h
🚨 49.0 business days
🗓️
3 Status: Scheduled Feb 25, 12:55 PM
Status: Scheduled → Technician Assigned → Dispatch Scheduled
👷
Technician Assigned by Megan Klose
Technician: Philmon Mehari
📅
Dispatch Scheduled by Megan Klose
Scheduled For: 2026-03-04T14:00:00.000+0000
⚠️ 5.0 business days
🔧
Status: Tech On Site by Philmon Mehari Mar 3, 6:59 PM
From: Scheduled
To: Tech On Site
Duration in Previous: 6d 6h
1.6 business days
🔩
Parts Added Mar 4, 9:42 PM
Type: Parts
Status: Open
Qty: 1
⏱️
2x Labor Added Mar 4, 9:54 PM
Type: Labor
Status: Open
Qty: 1, 1.5
💵
2 2x Expenses Added Mar 4, 10:08 PM
2x Expenses Added → Travel Added
🚗
Travel Added
Type: Travel
Status: Open
Qty: 36
💵
Expenses Added Mar 4, 10:35 PM
Type: Expenses
Status: Open
Qty: 1
✔️
Status: Completed by Philmon Mehari Mar 4, 10:53 PM
From: Tech On Site, Completed
To: Completed, Closed
Duration in Previous: 1d 3h, 0m

Bottlenecks

Entered
Duration: 2.0 business days (threshold: 4.0 business hours)
Exceeded by 1.5 business days
Scheduled
Duration: 4.8 business days (threshold: 2.0 business days)
Exceeded by 2.8 business days
Tech On Site
Duration: 1.5 business days (threshold: 1.0 business days)
Exceeded by 3.9 business hours

🔗 Related Artifacts

No related artifacts

ℹ️ Work Order Details

Status
Closed
Priority
PC
Type
FCO
Branch
N/A
Technician
Philmon Mehari
Scheduled
Mar 4, 9:00 AM
Created
Dec 12, 11:06 AM
Invoice #
N/A

Work Details (7)

Name Type Status Qty Amount Date
WL-03130870 Parts Open 1 $0.00 Mar 4, 9:42 PM
WL-03130886 Labor Open 1 $525.00 Mar 4, 9:54 PM
WL-03130887 Labor Open 1.5 $100.00 Mar 4, 9:54 PM
WL-03130922 Expenses Open 1 $0.00 Mar 4, 10:08 PM
WL-03130923 Expenses Open 1 $0.00 Mar 4, 10:09 PM
WL-03130935 Travel Open 36 $0.00 Mar 4, 10:11 PM
WL-03130943 Expenses Open 1 $0.00 Mar 4, 10:35 PM

Details