📍 MOSAIC LIFE CARE MEDICAL CENTER AT ST JOSEPH — 5325 FARAON ST, SAINT JOSEPH MO, 64506
Dec 12, 2025 → Feb 25, 2026
🔴 Behind
PC
SLA Clock
Per client agreement · Target: Feb 28, 2026
✓ SLA Met (2 biz days early)
Active: 6 biz days
Paused: 43 biz days
🕐 Clock stopped: Completed (Feb 25, 2026)
▶ Clock Running
Status: Created
Dec 12 → Dec 15, 2025
1 business day (counted)
Running total: 1 of ? biz days used
⏸43d
⏸ Clock Paused
Status: Ready for Release
Dec 15 → Feb 18, 2026
43 business days (not counted)
▶ Clock Running
Status: On Hold
Feb 18 → Feb 20, 2026
2 business days (counted)
Running total: 3 of ? biz days used
▶ Clock Running
Status: Assigned
Feb 20 → Feb 24, 2026
2 business days (counted)
Running total: 5 of ? biz days used
▶ Clock Running
Status: Scheduled
Feb 24 → Feb 25, 2026
1 business day (counted)
Running total: 6 of ? biz days used
Created: Dec 12, 2025Completed: Feb 25, 2026
Show SLA Clock Detail (5 periods)
Period
Status
Clock
Biz Days
Running Total
Dec 12 → Dec 15
Created
▶ Running
1
1
Dec 15 → Feb 18
Ready for Release
⏸ Paused
43
—
Feb 18 → Feb 20
On Hold
▶ Running
2
3
Feb 20 → Feb 24
Assigned
▶ Running
2
5
Feb 24 → Feb 25
Scheduled
▶ Running
1
6
Dispatch2.0d
Holding46.1d (excluded)
Coordinators3.7d
Field Work0.6d
✓ SLA Met
Dispatch
2.0 days
Over SLA
Holding(excluded from total)
46.1 days
Coordinators
3.7 days
Over SLA
Field Work
0.6 days
Created: Dec 12, 2025
Due: Feb 28, 2026 (5 days overdue)
📅
50.0 daysTotal Age
⏱️
43.8d in Ready for ReleaseLongest Stage
🔄
7 transitionsStatus Changes
⚠️
3.4d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
2 linesWork Details
🏠
1 visitOn-Site Trips
📋
CoordinatorScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
On Track
Ready to Bill • 82 days old
🚨
Primary Delay43.8 days stuck in "Ready for Release"
⏱️
Total Delay3.4 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
2.0d / 0.5d SLA
Ready for Release
43.8d
On Hold
2.3d
Assigned
2.3d / 0.5d SLA
Scheduled
1.3d / 2.0d SLA
Completed
0.6d / 1.0d SLA
Closed
1.1d / 1.0d SLA
💬 Activities, Notes & Communications
🔒Internal CSA Notes
02/02/2026; ARoosa- Called; 816-271-6000, Spoke to Biomed Dept. was asked to send email to: biomedgeneral@mymlc.com.
🔧Work Performed
FMI 78101 Not Required – FMI was previously completed
🔍Technician Findings
FMI 78101 Not Required – FMI was previously completed
⚠️Problem Description
FMI 78101C: Venue Fit Thermal Event due to battery Purpose: Each affected system will have a SW Version R3.5 update installed. FMI Type: Mandatory Recall FMI For code 2, 3, 4 and 5 closures, please reach out to FMI admin team at TCS.FMIAdmin@gehealthcare.com or 8668836784 – OPT. 5 for assistance in closing and correct objective evidence attachment to Activity/SR.
📞Call Description
FMI 78101
📧
Email: Field Action Notice - FMI 78101 - GE Healthcare - Venue Go/Fit Thermal Event - MOSAIC LIFE CARE MEDICAL CENTER AT ST JOSEPH - SAINT JOSEPH, MO - WO-01325845
Completed Feb 2, 2026
To:
CC: angela.roosa@emsar.com; deon.malloy@emsar.com; fmessak@emsar.com; central.scheduling@emsar.com
BCC:
Attachment: Vendor Letter for Customers 78101 EMSAR.pdf, FMI 78101 Customer Letter_DOC3115777_Rev2.pdf
Subject: Field Action Notice - FMI 78101 - GE Healthcare - Venue Go/Fit Thermal Event - MOSAIC LIFE CARE MEDICAL CENTER AT ST JOSEPH - SAINT JOSEPH, MO - WO-01325845
Body:
Good Afternoon,
I am contacting you on behalf of GE Healthcare about a Field Safety Notice issued for certain
📧
Live Call_Followed Up With Email
Completed Feb 2, 2026
02/02/2026; ARoosa- Called; 816-271-6000, Spoke to Biomed Dept. was asked to send email to: biomedgeneral@mymlc.com.
Timeline
📋
Work Order Created Dec 12, 11:06 AM
Work Order:WO-01325845
Type:FCO
Priority:PC
⏳2.0 business days
✅
Status: Ready for Release by Mandy NewmanDec 15, 12:12 PM