📍 Wythe County Community Hospital — 600 West Ridge Road, Wytheville VA, 24382
Jan 22, 2026 → Feb 19, 2026
✅ Completed
PSM
SLA Clock
Last business day of January 2026 · Target: Jan 30, 2026
✗ SLA Missed (13 biz days late)
Active: 20 biz days
🕐 Clock stopped: Completed (Feb 20, 2026)
▶ Clock Running
Status: Created
Jan 22 → Jan 22, 2026
0 business days (counted)
Running total: 0 of ? biz days used
15d
▶ Clock Running
Status: Ready for Scheduling
Jan 22 → Feb 12, 2026
15 business days (counted)
Running total: 15 of ? biz days used
5d
▶ Clock Running
Status: Assigned
Feb 12 → Feb 20, 2026
5 business days (counted)
Running total: 20 of ? biz days used
Created: Jan 22, 2026Completed: Feb 20, 2026
Show SLA Clock Detail (3 periods)
Period
Status
Clock
Biz Days
Running Total
Jan 22 → Jan 22
Created
▶ Running
0
0
Jan 22 → Feb 12
Ready for Scheduling
▶ Running
15
15
Feb 12 → Feb 20
Assigned
▶ Running
5
20
Dispatch0.0d
Coordinators21.1d
Field Work0.0d
Billing1.4d
✗ SLA Missed
Dispatch
0.0 days
Coordinators
21.1 days
Over SLA
Field Work
0.0 days
Billing
1.4 days
Over SLA
Created: Jan 22, 2026
Due: Feb 27, 2026
Completed: Feb 20, 2026 (7 days early)
📅
20.1 daysTotal Age
⏱️
16.0d in Ready for SchedulingLongest Stage
🔄
7 transitionsStatus Changes
⚠️
25.0d overTotal Delay
📦
0 orders, 0 quotesParts & Quotes
📝
1 linesWork Details
🏠
1 visitOn-Site Trips
📋
CoordinatorScheduling
AI Analysis
Powered by OpenAI
Generating AI analysis...
Completed with significant delays
Invoiced • 41 days old
🚨
Primary Delay16.0 days stuck in "Ready for Scheduling"
⏱️
Total Delay25.0 business days over SLA thresholds
SLA vs Actual Time by Status
Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.0d / 0.5d SLA
Ready for Scheduling
16.0d / 1.0d SLA
Assigned
5.1d / 0.5d SLA
Completed
0.0d / 1.0d SLA
Closed
6.0d / 1.0d SLA
Ready to Bill
1.4d / 1.0d SLA
Invoice Pending
0.0d / 2.0d SLA
💬 Activities, Notes & Communications
🔧Work Performed
Technician Findings upon arrival: Located unit in facility
What caused the issue: Annual PM Required
Actions Taken/Work Performed: Performed PM & followed instructed PM procedures
Final Resolution: All Functions are Working as Intended
Returned to Service
🔍Technician Findings
Technician Findings upon arrival: Located unit in facility
What caused the issue: Annual PM Required
Actions Taken/Work Performed: Performed PM & followed instructed PM procedures
Final Resolution: All Functions are Working as Intended
Returned to Service