Work Order 360 View

Detailed work order timeline, KPIs, and analysis

← WO Overview

WO-01299312 ↗ ServiceMax

NaphCare • Inspection • PSM

📍 NAPHCARE - MONTGOMERY COUNTY DETENTION FACILITY - 5106 — 225 S MCDONOUGH ST, MONTGOMERY AL, 36104

Aug 25, 2025 → Dec 23, 2025

✅ Completed
PSM
SLA Clock
Last business day of August 2025 · Target: Aug 29, 2025
✗ SLA Missed (77 biz days late)
Active: 82 biz days
🕐 Clock stopped: Completed (Dec 24, 2025)
▶ Clock Running
Status: Created
Aug 25 → Aug 25, 2025
0 business days (counted)
Running total: 0 of ? biz days used
▶ Clock Running
Status: Ready for Scheduling
Aug 25 → Sep 3, 2025
6 business days (counted)
Running total: 6 of ? biz days used
12d
▶ Clock Running
Status: Assigned
Sep 3 → Sep 19, 2025
12 business days (counted)
Running total: 18 of ? biz days used
▶ Clock Running
Status: Entered
Sep 19 → Sep 19, 2025
0 business days (counted)
Running total: 18 of ? biz days used
▶ Clock Running
Status: Ready for Scheduling
Sep 19 → Sep 19, 2025
0 business days (counted)
Running total: 18 of ? biz days used
▶ Clock Running
Status: Assigned
Sep 19 → Sep 24, 2025
3 business days (counted)
Running total: 21 of ? biz days used
▶ Clock Running
Status: Entered
Sep 24 → Sep 24, 2025
0 business days (counted)
Running total: 21 of ? biz days used
30d
▶ Clock Running
Status: On Hold
Sep 24 → Nov 6, 2025
30 business days (counted)
Running total: 51 of ? biz days used
▶ Clock Running
Status: Ready for Scheduling
Nov 6 → Nov 14, 2025
5 business days (counted)
Running total: 56 of ? biz days used
18d
▶ Clock Running
Status: Assigned
Nov 14 → Dec 12, 2025
18 business days (counted)
Running total: 74 of ? biz days used
▶ Clock Running
Status: Scheduled
Dec 12 → Dec 19, 2025
5 business days (counted)
Running total: 79 of ? biz days used
▶ Clock Running
Status: Tech On Site
Dec 19 → Dec 19, 2025
0 business days (counted)
Running total: 79 of ? biz days used
▶ Clock Running
Status: Tech Off Site
Dec 19 → Dec 22, 2025
1 business day (counted)
Running total: 80 of ? biz days used
▶ Clock Running
Status: Scheduled
Dec 22 → Dec 23, 2025
1 business day (counted)
Running total: 81 of ? biz days used
▶ Clock Running
Status: Tech On Site
Dec 23 → Dec 24, 2025
1 business day (counted)
Running total: 82 of ? biz days used
Created: Aug 25, 2025 Completed: Dec 24, 2025
Show SLA Clock Detail (15 periods)
Period Status Clock Biz Days Running Total
Aug 25 → Aug 25 Created ▶ Running 0 0
Aug 25 → Sep 3 Ready for Scheduling ▶ Running 6 6
Sep 3 → Sep 19 Assigned ▶ Running 12 18
Sep 19 → Sep 19 Entered ▶ Running 0 18
Sep 19 → Sep 19 Ready for Scheduling ▶ Running 0 18
Sep 19 → Sep 24 Assigned ▶ Running 3 21
Sep 24 → Sep 24 Entered ▶ Running 0 21
Sep 24 → Nov 6 On Hold ▶ Running 30 51
Nov 6 → Nov 14 Ready for Scheduling ▶ Running 5 56
Nov 14 → Dec 12 Assigned ▶ Running 18 74
Dec 12 → Dec 19 Scheduled ▶ Running 5 79
Dec 19 → Dec 19 Tech On Site ▶ Running 0 79
Dec 19 → Dec 22 Tech Off Site ▶ Running 1 80
Dec 22 → Dec 23 Scheduled ▶ Running 1 81
Dec 23 → Dec 24 Tech On Site ▶ Running 1 82
Dispatch 0.0d
Holding 30.9d (excluded)
Coordinators 56.4d
Field Work 3.6d
Billing 0.0d
✗ SLA Missed
Dispatch
0.0 days
Holding (excluded from total)
30.9 days
Coordinators
56.4 days
Over SLA
Field Work
3.6 days
Over SLA
Billing
0.0 days
Created: Aug 25, 2025 Due: Nov 26, 2025 Completed: Dec 24, 2025 (27 days late)
📅
82.6 days Total Age
⏱️
30.9d in On Hold Longest Stage
🔄
13 transitions Status Changes
⚠️
49.5d over Total Delay
📦
0 orders, 0 quotes Parts & Quotes
📝
27 lines Work Details
🚩
4 visits On-Site Trips
👤
Self-Scheduled Scheduling
🚩
4 On-Site Visits
4 on-site visits — why were multiple trips needed?
👤 Self-scheduled by Cynthia G Deville — scheduling delays attributed to technician, not coordinators
Visit 1 Dec 17, 2025
Visit 2 Dec 18, 2025
Visit 3 Dec 22, 2025
Visit 4 Dec 23, 2025

AI Analysis

Powered by OpenAI
Generating AI analysis...

Originating Case

Open in Salesforce →
🎫
Case #00521578
eBiotrack - Automated New Inspection Created
Closed
Inspection: Annual Equipment Electrical Safety Test And Calibration Service 28 pcs https://www.ebiotrack.com/inspection.php?iid=29532 Inspection Flag: As of 12/7 NEEDS APPROVAL FOR ANY REPAIR OVER $500.
Priority
Standard
Origin
Email
Reason
New Case
Contact
Michael Hayden
Owner
Jessica Sells
Created
Aug 25, 2025
Work Orders from this Case (1)
WO-01299312 (current) Invoiced
Inspection • Cynthia G Deville
Created: Aug 25, 2025 • Closed: Dec 23, 2025
Completed with significant delays
Invoiced • 191 days old
🚨
Primary Delay 30.9 days stuck in "On Hold"
⏱️
Total Delay 49.5 business days over SLA thresholds

SLA vs Actual Time by Status

Actual (within SLA)
Actual (over SLA)
SLA Target
Entered
0.0d / 0.5d SLA
Ready for Scheduling
13.0d / 1.0d SLA
Assigned
35.4d / 0.5d SLA
On Hold
30.9d
Scheduled
8.0d / 2.0d SLA
Tech Off Site
2.0d / 2.0d SLA
Tech On Site
1.6d / 1.0d SLA
Closed
1.0d / 1.0d SLA
Invoice Pending
0.0d / 2.0d SLA

💬 Activities, Notes & Communications

🔒 Internal CSA Notes

CONFIRMED

12/22/25 AJinerson - Sent confirmation email back to LaKeshia and Deonne confirming the below scheduled return service.

12/22/25 AJinerson - Received confirmation email from LaKeshia Maddox confirming tech return visit to complete inspection on Tuesday, 12/23 with arrival between 9am-11am.


12/19/25 AJinerson - Sent follow up email back to Deonne and LaKeshia offering tech visit to return on Tuesday, 12/23 with eta between 9am-11am.

(tech would overnight 12/22 to start with morning arrival for this service)


12/19/25 AJinerson - Spoke with FSE, needs 1/2 day back onsite.

12/12/25 AJinerson - Sent email back to POC Deonne and LaKeshia confirming we have tech scheduled for 12/18 between 9am-11am arrival. Asking for any further requirements and/or arrival instructions needed.


12/12/25 RBerry- Received confirmation from Deonne Hopkins to schedule for 12/18/25 with arrival time between 9-11AM. See logged email.


12/11/25 AJinerson - Sent follow up email to Deonne and LaKeshia offering tech visit on Thurs. 12/18 with eta between 9am-11am.

(tech may have to overnight evening before).

Site said arrival must be between 9am-12pm.


12/11/25 AJinerson - Assigned FSE does not yet have HCP stickers, followed up with tech sup to check on ETA for those so we can get this scheduled asap.


12/11/25 AJinerson - Received email back from LaKeshia Maddox confirming they have approved clearance for tech: Cynthia Deville and ready to schedule now. Sent email back to LaKeshia asking what days of the week/times the facility would be available for service.


12/9/25 AJinerson - Received email back from Deonne Hopkins confirming they have received the paperwork and driver's license and have submitted to the custody staff to get approval. They will notify us once they have received approval.


12/9/25 AJinerson - Sent email back to Deonne and LaKeshia asking them to please let us know if they need anything further and to please let us know once they have approval for clearance so we can proceed with scheduling service visit.


12/9/25 AJinerson - Received email back from Deonne that they still need tech's ID. Tech confirmed they sent copy of ID to contacts via email.


12/4/25 AJinerson - Email to POC LaKeshia Maddox asking to confirm if they have received the approval on clearance yet to proceed with scheduling service.


12/2/25 AJinerson - FSE CDeville resubmitted paperwork/clearance form back to LaKeshia. Awaiting confirmation from LaKeshia to proceed with scheduling once clearance approved.


11/26/25 AJinerson - Currently awaiting confirmation from customer to approve when tech's background form has been cleared to proceed with scheduling.

11/24/25 AJinerson - Email back to LaKeshia requesting to please inform us once they receive the form and ready to proceed with scheduling.


11/24/25 AJinerson - Received email from additional contact, LaKeshia Maddox stating they have not received the form yet.

FWD to tech requesting to please complete form and send back to LaKeshia as well.

11/24/25 AJinerson - Sent follow up email to Deonne to check in to see if we have received approval/clearance yet to proceed with scheduling since our tech submitted the clearance form for this facility.


11/21/25 AJinerson - FSE CDeville submitted paperwork to customer. We are just now awaiting confirmation from customer for approval to proceed with scheduling.


11/19/25 RBerry- Updated due date based on release of WO due to contact issues.


11/17/25 AJinerson - Awaiting FSE to submit paperwork for clearance. Customer to let us know once confirmed clearance.

11/14/25 AJinerson - Sent email to POC Deonne informing them that tech has form to fill out and will return it to Deonne along with photocopy of ID.

Requesting Deonne to let us know once we have approval/clearance to proceed with scheduling accordingly.


11/14/25 AJinerson - Assigned FSE is to fill out form and return back to contact:

Deonne Hopkins at deonne.hopkins@naphcare.com


11/6/25 AJinerson - WO went back into RFS past the SLA due to contact unavailable.


Scheduling ahead needed: Yes. please call 334 832 7108-Ms. Maddox. Also, a background form must be completed before the scheduled visit. The background form is attached. Also, a copy of the front and back of the Drivers license must be sent as well.

Certain day or time: Mornings are better

Confirmed contact information is correct: Yes 

Anything additional needed for tech to gain access to the facility: Yes. background check required.


11/06/2025 LHill-sent email to Abby with background check form.


11/06/2025 LHill-rec'd email from Deonne Baker-Hopokins-she sent a wavier form for tech to fill out. Is there a particular day or time that typically works best for your facility? Mornings are better

  1. Would you like the technician to call ahead before arriving? Yes, please call 334 832 7108-Ms. Maddox. Also, a background form must be completed before the scheduled visit. The background form is attached. Also, a copy of the front and back of the Drivers license must be sent as well.
  2. Is there anything additional needed for our technician to gain access to your facility? see #2


see logged email.


11/06/2025 LHill-sent email to Deonne Baker-Hopkins at deonne.hopkins@naphcare.com to confirm contact & equipment.


11/6/2025 DNakoff - Updated POC


9/24/25 AJinerson - Clearing tech name and escalating to ASM due to poor contact.


9/24/25 AJinerson - Called site 3rd time to follow up and schedule tech visit. No one available to take call, and no option for VM. 


9/8/25 AJinerson - Called site again and tried different prompt (334) 832-4985. Left VM for staff regarding 


9/8/25 AJinerson - Called site (334) 832-4985. No answer, no option for VM. 


9/8/25 AJinerson - Site number from google (334) 832-4985


9/5/25 AJinerson - Sent follow up email to POC Michael offering tech visit 9/10 with eta between 1230pm-130pm.


9/3/25 AJinerson - No phone number listed. Sent email to POC Michael offering tech visit 9/10 with eta between 1230pm-130pm.

🔧 Work Performed
SCANNER NOT CONNECTING TO PC, FORCED TO ENTER INFORMATION MANUALLY ALL WALL TRANSFORMER UNITS DO NOT HAVE THEIR POWER CORDS CONNECTED. SOME ARE MISSING LIIGHT HEADS. WAS ABLE TO TEST WHEN FOUND POWER CORD IN A DRAWER. ON SITE CONTACT STATED THAT THEY WERE NOT USED. THE MANUAL MANOMETERS ATTACHED TO THESE UNITS ALSO DID NOT HAVE CUFFS ATTACHED AND HAD TO SEARCH TO LOCATE ATTACHING BULBS AND CUFF ASSEMBLIES. WAS UNABLE TO COMPLETE THE ENTIRE INSPECTION AS NUMEROUS UNITS NOT PREVIOUSLY IDENTIFIED WERE LOCATED AND ADDED TO THE INVENTORY. CONTACTING POINT OF CONTACT ON FRIDEAY TO CONFIRM RETURN ON 12/22 TO COMPLETE THE INSPECTION. 12/22/25 INSPECTION COMPLETED
🔍 Technician Findings
Onsite to perform inspection
⚠️ Problem Description
Inspection: Annual Equipment Electrical Safety Test And Calibration Service 28 pcs https://www.ebiotrack.com/inspection.php?iid=29532 Inspection Flag: As of 12/7 NEEDS APPROVAL FOR ANY REPAIR OVER $500.

Timeline

📞
Case Linked Aug 25, 1:00 AM
Case Number: 00521578
Subject: eBiotrack - Automated New Inspection Created
Status: Closed
📋
2 Work Order Created Aug 25, 9:47 AM
Work Order Created → Status: Ready for Scheduling
📅
Status: Ready for Scheduling by Jessica Sells
From: Entered
To: Ready for Scheduling
Duration in Previous: 0m
⚠️ 7.0 business days
👷
2 Technician Assigned Sep 3, 10:57 AM
Technician Assigned → Status: Assigned
👷
Status: Assigned by Abby Jinerson
From: Ready for Scheduling
To: Assigned
Duration in Previous: 9d 1h
🚨 13.0 business days
🆕
2 Status: Entered Sep 19, 1:28 PM
Status: Entered → Technician Assigned
👷
Technician Assigned by Abby Jinerson
Technician: Dylan Ingraham
4.0 business days
🆕
Status: Entered by Abby Jinerson Sep 24, 12:57 PM
From: Assigned, Entered
To: Entered, On Hold
Duration in Previous: 4d 23h, 0m
🚨 31.0 business days
📅
Status: Ready for Scheduling by Dylan Nakoff Nov 6, 10:13 AM
From: On Hold
To: Ready for Scheduling
Duration in Previous: 42d 22h
⚠️ 6.0 business days
👷
2 Technician Assigned Nov 14, 2:12 PM
Technician Assigned → Status: Assigned
👷
Status: Assigned by Abby Jinerson
From: Ready for Scheduling
To: Assigned
Duration in Previous: 8d 3h
🚨 19.0 business days
📅
2 Dispatch Scheduled Dec 12, 9:21 AM
Dispatch Scheduled → Status: Scheduled
🗓️
Status: Scheduled by Ben Saur
From: Assigned
To: Scheduled
Duration in Previous: 27d 19h
💵
2x Expenses Added Dec 12, 11:39 AM
Type: Expenses
Status: Open
Qty: 1
⚠️ 5.9 business days
🔧
Status: Tech On Site by Cynthia Deville Dec 19, 7:02 AM
From: Scheduled, Tech On Site
To: Tech On Site, Tech Off Site
Duration in Previous: 6d 21h, 0m
🚗
2 7x Travel Added Dec 19, 7:18 AM
7x Travel Added → 4x Expenses Added
💵
4x Expenses Added
Type: Expenses
Status: Open
Qty: 1
2.0 business days
📅
2 Dispatch Scheduled Dec 22, 8:59 AM
Dispatch Scheduled → Status: Scheduled
🗓️
Status: Scheduled by Abby Jinerson
From: Tech Off Site
To: Scheduled
Duration in Previous: 3d 1h
💵
2x Expenses Added Dec 22, 9:43 AM
Type: Expenses
Status: Open
Qty: 1
2.0 business days
🔧
Status: Tech On Site by Cynthia Deville Dec 23, 10:19 AM
From: Scheduled
To: Tech On Site
Duration in Previous: 1d 1h
⏱️
2 12x Labor Added Dec 23, 11:58 PM
12x Labor Added → Status: Completed
✔️
Status: Completed by Cynthia Deville
From: Tech On Site, Completed
To: Completed, Closed
Duration in Previous: 13h 39m, 0m
📄
2 Status: Ready to Bill Dec 24, 11:12 AM
Status: Ready to Bill → Status: Invoiced
💰
Status: Invoiced by Diane Patton
From: Invoice Pending
To: Invoiced
Duration in Previous: 0m
3.0 business days
🧾
Invoice Created Dec 29, 8:28 AM
Invoice Number: SM-249899

Bottlenecks

Ready for Scheduling
Duration: 7.0 business days (threshold: 1.0 business days)
Exceeded by 6.0 business days
Assigned
Duration: 13.0 business days (threshold: 4.0 business hours)
Exceeded by 12.5 business days
Assigned
Duration: 3.8 business days (threshold: 4.0 business hours)
Exceeded by 3.3 business days
Ready for Scheduling
Duration: 6.0 business days (threshold: 1.0 business days)
Exceeded by 5.0 business days
Assigned
Duration: 18.6 business days (threshold: 4.0 business hours)
Exceeded by 18.1 business days
Scheduled
Duration: 6.0 business days (threshold: 2.0 business days)
Exceeded by 4.0 business days
Tech On Site
Duration: 1.6 business days (threshold: 1.0 business days)
Exceeded by 5.0 business hours

🔗 Related Artifacts

📞
Case 00521578
Closed

ℹ️ Work Order Details

Status
Invoiced
Priority
PSM
Type
Inspection
Branch
Edge
Technician
Cynthia G Deville
Scheduled
Dec 23, 9:00 AM
Created
Aug 25, 9:47 AM
Invoice #
SM-249899

Work Details (27)

Name Type Status Qty Amount Date
WL-03035781 Expenses Open 1 $0.00 Dec 12, 11:39 AM
WL-03035782 Expenses Open 1 $0.00 Dec 12, 11:39 AM
WL-03042951 Travel Open 184 - Dec 19, 7:18 AM
WL-03042947 Labor Open 6 $0.00 Dec 19, 7:18 AM
WL-03042948 Labor Open 3.25 $0.00 Dec 19, 7:18 AM
WL-03042949 Travel Open 174 - Dec 19, 7:18 AM
WL-03042950 Travel Open 11 - Dec 19, 7:18 AM
WL-03042945 Labor Open 3.25 $0.00 Dec 19, 7:18 AM
WL-03042946 Labor Open 0.25 $0.00 Dec 19, 7:18 AM
WL-03042953 Expenses Open 1 $0.00 Dec 19, 7:20 AM
WL-03042954 Expenses Open 1 $0.00 Dec 19, 7:20 AM
WL-03042955 Expenses Open 1 $0.00 Dec 19, 7:20 AM
WL-03042952 Expenses Open 1 $0.00 Dec 19, 7:20 AM
WL-03044989 Expenses Open 1 $0.00 Dec 22, 9:43 AM
WL-03044990 Expenses Open 1 $0.00 Dec 22, 9:43 AM
WL-03047068 Labor Open 2.5 $0.00 Dec 23, 11:58 PM
WL-03047069 Labor Open 0.5 $0.00 Dec 23, 11:58 PM
WL-03047070 Labor Open 4.25 $1,855.00 Dec 23, 11:58 PM
WL-03047071 Labor Open 2.5 $0.00 Dec 23, 11:58 PM
WL-03047072 Travel Open 112 - Dec 23, 11:58 PM
WL-03047073 Travel Open 11 - Dec 23, 11:58 PM
WL-03047074 Travel Open 130 - Dec 23, 11:58 PM
WL-03047075 Expenses Open 1 $0.00 Dec 23, 11:58 PM
WL-03047076 Expenses Open 1 $0.00 Dec 23, 11:58 PM
WL-03047077 Expenses Open 1 $0.00 Dec 23, 11:58 PM
WL-03047078 Expenses Open 1 $0.00 Dec 23, 11:58 PM
WL-03047079 Expenses Open 1 $0.00 Dec 23, 11:58 PM

Details