10/30 MOwens Lauren replied back that 11/6 or 11/7 would work for the inspection visit. Sent reply back to her scheduling the visit on 11/6 between 9-3.
10/30 MOwens Called to speak to Laurena Hopper. Left vm about scheduling the inspection during November. Sent email also.
🔧Work Performed
11/06/2025 - JWD Located all equipment that needs to be inspected for annual inspection on equipment and performed annual inspection, calibration and electrical safety tests for this site. Added all equipment that needs to be inspected equipment inspection, calibration and electrical safety tests for this site. Archived any equipment no longer in use Total of equipment inspected is 68. Notified POC Raheem Cade of inspection findings and completion. Completed final assessment of the inspection going over with POC the equipment that have been added to inventory and the ones added to archives.
🔍Technician Findings
11/06/2025 - JWD Locate all equipment that needs to be
inspected for annual inspection on equipment and perform annual inspection, calibration and electrical safety tests for this site. Add all equipment that is no longer in use to archives. Notify POC of the changes
⚠️Problem Description
Inspection: Annual Equipment Electrical Safety Test And Calibration Service
68 pcs
https://www.ebiotrack.com/inspection.php?iid=29824
From: mowens@emsar.com
To: Laurena.Hopper@hcahealthcare.com
Ok. I will schedule the visit for Thurs. 11/6 between 9-3.
Thanks
Melissa
From: Hopper Laurena <Laurena.Hopper@hcahealthcare.com>
Sent: Thursday, October 30, 2025 2:19 PM
To: Melissa Owens <mowens@emsar.com>
Subject: Re:CareNow Urgent Care - Murfreesboro TN Annual Tagged Equipment Inspection
Yes! Either one of those are fine.
Laurena Hopper
Center Manager II | CareNow Nashville
Urgent Care, HCA
📧
Email:CareNow Urgent Care - Murfreesboro TN Annual Tagged Equipment Inspection
Completed Oct 30, 2025
From: mowens@emsar.com
To: laurena.hopper@hcahealthcare.com
Laurena
It is time again in November to complete the annual inspection on the tagged medical equipment at this location. Please let me know what days during the week work the best to schedule the inspection visit.
Thanks
Melissa Owens
Account Service Coordinator
East District
mowens@emsar.com <mailto:mowens@emsar.com>
www.emsar.com <http://www.emsar.com/>
803-791-1259
<https://www.facebook.com/
📋
Outbound to +16155562623
Completed Oct 30, 2025
Called to speak to Laurena Hopper. Left vm about scheduling the inspection during November.