12/4/2025 CRamen logged email confirming Monday 2/7/2026 with an arrival window between 8-10am.
12/4/2025 CRamen logged email requesting Monday 2/7/2026 with an arrival window between 8-10am. Placeholder set
🔧Work Performed
Annual Inspection - Completed Annual Safety and Function testing on 50 equipment.
🔍Technician Findings
Completed Annual Safety and Function testing on 50 equipment.
⚠️Problem Description
Annual Equipment Electrical Safety Test And Calibration Service
Equipment 50
https://www.ebiotrack.com/inspection.php?iid=31689
📧
Email:RE: EMSAR Request for service at Centerwell - 06671 - Eastside (Email to schedule service)
Completed Dec 4, 2025
From: jmarlette@centerwell.com
To: cramen@emsar.com
Hi, Yes, that will be fine. I had previously requested service before end of the year because we have had so many changes to the equipment in the center. However, 2/7 will be ok- if that is the first available. Thanks,Jennifer Jennifer Marlette Center Administrator AssistantCenterWell-Eastside601 Versailles Rd.Frankfort, KY 40601JMarlette@centerwell.com From: Charles Ramen <cramen@emsar.com> Sent: Thursday, December 4, 2025 4:50 PMTo: J
📧
Email: EMSAR Request for service at Centerwell - 06671 - Eastside (Email to schedule service)
Completed Dec 4, 2025
To: jmarlette@centerwell.com
CC:
BCC: cramen@emsar.com
Attachment: --none--
Subject: EMSAR Request for service at Centerwell - 06671 - Eastside (Email to schedule service)
Body:
Hi Jennifer Marlette,
I hope you’re doing well. I’m reaching out to schedule a service appointment for Annual Equipment Electrical Safety Test And Calibration Service
Equipment 50
Here’s the location information we have on file:
Location:
Centerwell - 06671 - Eastside
601 Versailles Rd
Frankfort, KY 40601
Cont