15L
SYS-LC-1200
Contract ends 06/30/2026 repair included
PMPLUS / EOQ
PM Plus - allows a lamp to be ordered and consumed on a PM if needed. Sometimes a lamp may have been installed recently, so a new lamp is not needed at time of PM. The tech needs to ask the customer these questions when scheduling the PM for a PM PLUS. PM PLUS = UV lamp is included in the service.
G1316A-B
DE60556321 1200 Thermostatted Column Compartment
G1322A
JP60653334 1260 Standard Degasser
G1314B
DE60555663 1260 Variable Wavelength Detector VL
G1329A
DE60556021 1200 Series Standard Autosampler
G1311A-B
DE60555788 1200 Series Quaternary Pump
11-11-HSolano-Travel ''To Site" is in WO-01313400.
10/31/25 lcoonrod
Per email from Hermilo, The customer had mentioned that the annual PMOQ had already been completed earlier this year, so it was removed from my assignments, but it seems that Agilent wanted to re-qualify these systems again before they get decommissioned/ stop service (next year). Which is why it was added again to my assignments. I will complete this service next week.
Please assign to Hermilo Solano ARP to site is 46 miles. Zone 1
🔧Work Performed
Performed annual PMOQ per BACHEM custom EQP.
All PMOQ tests passed. The CD file containing the EQR was given to customer.
🔍Technician Findings
N/A
⚠️Problem Description
15L
SYS-LC-1200
Contract ends 06/30/2026 repair included
PMPLUS / EOQ
PM Plus - allows a lamp to be ordered and consumed on a PM if needed. Sometimes a lamp may have been installed recently, so a new lamp is not needed at time of PM. The tech needs to ask the customer these questions when scheduling the PM for a PM PLUS. PM PLUS = UV lamp is included in the service.
G1316A-B
DE60556321 1200 Thermostatted Column Compartment
G1322A
JP60653334 1260 Standard Degasser
G1314B
DE60555663 1260 Variable Wavelength Detector VL
G1329A
DE60556021 1200 Series Standard Autosampler
G1311A-B
DE60555788 1200 Series Quaternary Pump
📄Description
1200 Quaternary Pump
📞Call Description
AUG 2025 LC EOQ
Oct 31, 2025 8:33am
@Hermilo Solano Agilent is asking why this SO was not completed. I know at one time, they had it assigned to an Agilent tech, then asked that it be re-assigned to you. I believe that was the end of Oct. Please advise.